| 2004 |
Founding of the company |
| 2005 |
Purchase of seven injection moulding machines |
| 2009 |
Purchase of four injection moulding machines |
| 2012 |
Purchase of three injection moulding machines |
| 2015 |
Obtaining a building permit for the construction of a production hall with an office building |
| 2016 |
Beginning of construction |
| 2016 |
Purchase of tree injection moulding machines |
| 2016 |
Purchase of a central cooling system |
| 2016 |
Purchase of an overhead crane |
| 2017 |
Start of production in the new production hall |
| 2018 |
Purchase of two injection moulding machines |
| 2018 |
Purchase of a Venture 3D measuring machine |
| 2019 |
Purchase of three injection moulding machines |
| 2020 |
Purchase of two injection moulding machines |
| |
|
| |
|
| |
|
| |
|
| |
|
| |
|
| |
|